This design-build project consisted of designing the new marina, demolishing the existing wood docks, piles and gangways, and dredging to a depth of -12 feet. Over 100,000 cubic yards of sediment were removed, with disposal of 15,000 cubic yards of contaminated material at an upland site.
The project consisted of furnishing and installing new concrete docks to create 385 slips of various lengths and widths, driving over 400 piles, upgrading utilities services, and building a fixed sheet pile wall breakwater. The capstone of the project involved design, fabrication and installation of a 225 foot floating wave attenuator to protect the marina entrance.
Major Challenges
Keeping the marina operational and existing facilities intact during construction was a major challenge. Dutra implemented a strategic project phasing plan that allowed for up to two hundred boats of varying lengths to remain inside the marina throughout construction.
Project Scope
Demolition of existing floating docks, piles and gangways.
Fabrication and installation of new floating concrete docks to create a modern 385 slip state-of-the-art marina.
Replacement and reconfiguration of the gates, platforms and gangways.
Dredging, capping, and upland disposal of contaminated sediments.
Seawall repair and new seawall construction.
Fixed sheet pile wall and floating concrete breakwater construction.
Installation of a new sewer pump out station.
New electrical, water and communication services; fire suppression systems, security system and lighting service on all docks.